How to Keep Yacht Refit Change Orders Under Control

Learn how to price refit extras, control approval authority and track the final bill, with a worked €500,000 budget example.

RefitPublished October 27, 20267 min read

The cheapest quotation may simply contain less work

Before negotiating extras, establish exactly what the original price buys. Give each job a reference number and attach its specification to the contract. “Service air-conditioning” is not a specification; identify the equipment, the servicing operations, the replacement parts included and the acceptance test.

For a chilled-water system, for example, ask the yard to distinguish cleaning strainers from chemically cleaning the circuit, replacing circulation pumps and investigating poor cabin airflow. Keep fault-finding separate from the corrective work that investigation may reveal.

Build a comparison sheet rather than comparing the totals on two quotations. Include these often-overlooked lines:

  • Removal and reinstatement of joinery needed for access.
  • Protection of finished surfaces and cleaning after completion.
  • Crane movements, scaffolding and equipment hire.
  • Hardstanding, shore power and waste disposal.
  • Freight and visiting technicians’ travel expenses.
  • Commissioning, testing and any required survey attendance.

A useful discipline is to maintain separate columns for budget estimates and actual quotations, then multiply daily charges by the planned yard period. This approach also appears in the current refit-governance guidance, which specifically calls for checking exclusions and logistics costs.

Ask for photographs or an inspection before pricing inaccessible work. Where inspection is impossible without dismantling, buy a defined investigation first. Do not ask the yard to guarantee the condition of machinery it has not opened.

Azimut 35,3 m « OCEAN ONE » — Banquettes et moteurs de l'annexe
Azimut Grande 36M "OCEAN ONE", for sale →

A fixed price needs boundaries, not a reassuring label

For a defined installation, seek a fixed price against an agreed specification. For investigation or uncertain repairs, negotiate time-and-materials work with an approval ceiling. State what happens at that ceiling: stop safely, report findings and obtain further authority.

Treat a provisional allowance as a placeholder until the contract explains otherwise. A €12,000 allowance for exhaust repairs should not quietly become permission to spend whatever the eventual repair costs. Require an updated proposal once the components are exposed.

Read the incorporated general conditions as carefully as the quotation. Published ship-repair terms revised for 2026 demonstrate the issue: extra work can be charged at rates applicable when it is performed, while classification costs and taxes can sit outside agreed prices. Those are terms of that particular contract, not universal rules.

Before signing, settle the following commercially:

  • Trade-specific hourly rates and the period for which they remain valid.
  • Overtime approval and applicable premiums.
  • Materials and subcontractor markups.
  • Handling charges for owner-supplied equipment or direct contractors.
  • Daily charges if the yacht stays longer than planned.
  • The order of precedence between negotiated terms and printed conditions.

For legal interpretation and enforceability, have a qualified adviser confirm the position for the particular contract and jurisdiction.

Do not invent a retention after the final invoice arrives. If part of the price is to remain unpaid until defects are cleared, negotiate the amount and release conditions before work starts.

Every extra needs a price and a calendar consequence

Use one numbered variation register shared by the yard and the owner’s representative. A message saying “go ahead” should identify the proposal being approved, not leave everyone reconstructing the conversation in April.

The established refit framework provides a Variation Certificate template in Schedule IV and requires changes to be recorded in writing. Use that discipline even if the yard works under a different negotiated contract.

A practical approval sequence is:

  1. Record the finding or requested change against the original job number, with photographs where useful.
  2. Establish why it is outside the agreed scope, rather than correction of an incomplete original job.
  3. Obtain the proposed remedy, alternatives and itemised price, including any credit for deleted work.
  4. Record effects on purchasing, access, testing and the contractual redelivery date.
  5. Obtain approval from the named authorised person before proceeding, subject to agreed emergency powers.

Keep the emergency exception narrow: immediate action to protect the yacht or people is different from ordering a nicer dashboard while the electrician is aboard. Agree how emergency expenditure will be reported and documented.

Also define authority. For example, the captain might approve up to €2,500 per variation within an aggregate limit, while anything affecting redelivery requires owner approval. These are suggested controls, not standard contractual thresholds.

A common mistake is authorising a €4,000 component without asking what installation requires. Removing a ceiling, fabricating a bracket and returning a specialist to commission it belong in the same decision.

Azimut Leonardo 98 « SIMONA » — Le barbecue du flybridge
Azimut Leonardo 98 "SIMONA", for sale →

Watch committed spending, not just paid invoices

A yacht can look comfortably below budget while expensive equipment is already ordered and several repair proposals remain unanswered. Request a weekly forecast showing original scope, approved variations, pending proposals and the expected cost to finish.

Keep contingency outside individual work-package prices. For planning, consider testing the budget with a 15% reserve for a tightly specified project and a 25% reserve where substantial hidden-condition risk remains. These are suggested stress tests, not published market averages or assurances that the reserve will suffice.

If either scenario makes the project unaffordable, reduce elective scope before arrival. Do not rely on negotiating away necessary repairs once the yacht is dismantled.

Keep owner upgrades separate from discovery costs. Replacing a corroded pipe and choosing new saloon lighting are different decisions. Combining them under “unforeseen works” hides the reason the budget moved.

Labour timing deserves particular attention. Fairhaven Shipyard’s published rates effective May 1, 2026 list electrical and mechanical work at $135 per hour and overtime at $202.50, with double time on Sundays and holidays. These are one yard’s rates, not a US-wide benchmark.

At those listed electrical rates, 100 hours cost $13,500 in normal time or $20,250 at the stated overtime rate. Before approving overtime to recover a slipping schedule, ask which completion milestone those hours will actually bring forward.

A €500,000 refit can become €622,000 without a spectacular failure

Consider an illustrative 24-metre motor yacht entering a Mediterranean yard in November for a planned March redelivery. The following figures are planning assumptions, not quotations or market averages.

The owner authorises this base budget:

  • Defined yard works: €420,000.
  • Owner-appointed specialists and project oversight: €35,000.
  • Yard services and equipment hire: €25,000.
  • Testing, delivery and other project expenses: €20,000.

The base is €500,000. A separately held 20% contingency adds €100,000, giving €600,000 of available project funding before any applicable taxes.

During dismantling, the yard identifies a leaking chilled-water pipe behind guest-cabin joinery. The variation totals €22,000: €14,000 for pipework and €8,000 for access and reinstatement. The agreed proposal fits within the existing programme.

The owner then requests €48,000 of upgraded electronics. Assume this change genuinely pushes redelivery back by three weeks. Under the example’s agreed rates, additional yard services cost €12,000 and extra owner-side attendance and accommodation cost €8,000.

Finally, investigative work produces another €32,000 of necessary repairs. Total additions are €122,000, bringing the project to €622,000, or €22,000 above available funding.

The electronics decision consumed €68,000 once its assumed schedule consequences were counted. Without it, the necessary works would have taken the project to €554,000, leaving €46,000 of contingency.

That distinction matters. The owner did not suffer an unexplained €122,000 overrun: €54,000 addressed discovered defects and €68,000 followed an elective decision. Record both honestly, then decide whether the upgrade justifies the lost time and money.

Cayman Yachts 27 m « CECILOU » — Vue d'ensemble du flybridge
Cayman Yachts 27 m "CECILOU", for sale →

Protect the departure date before the final invoice

Give pending variations decision deadlines tied to the programme. Ask the yard to identify the latest approval date that preserves the agreed completion date, and put that information beside the price.

The refit framework’s Clause 7.2 addresses prolongation costs arising from matters for which the owner is responsible. Its guidance also identifies delayed owner decisions and owner-appointed contractors as potential grounds for permissible delay. A late approval can therefore have consequences beyond the added work itself.

For a yacht needed in Antibes in May, work backwards from an operational departure date, not simply launch day. Reserve a separate period for commissioning, trials and rectification in the agreed programme.

During the final month, reconcile every approved variation against the invoice register. Require deleted work to show as a credit, and check that access labour has not been charged twice across overlapping jobs.

Before accepting a machinery installation, ask for its agreed test results and warranty documentation. Before closing a concealed repair, arrange inspection and photographs. Make acceptance evidence part of each job’s definition rather than an argument at handover.

The last trap is approving “small” extras because departure feels close. Keep applying the same authority limits until the yacht leaves. A late discretionary job should earn its place in the programme, not gain approval merely because the tools are still aboard.

In short

  • Define access, reinstatement and testing in the original scope so necessary work is not mistaken for an extra.
  • Approve each variation with its full price, deleted-work credits and redelivery consequences.
  • Review committed spending and the forecast final cost weekly, not just paid invoices.
  • Hold contingency separately and distinguish discovered defects from elective upgrades.
  • Agree approval authority, prolongation charges and handover evidence before the yacht enters the yard.

General information only: rules, taxes and prices change and depend on your situation. Check with a qualified adviser before deciding.

A question about your own project?

Tell me what you are planning: you get a straight answer, for your case.